Tyrol Truck Dosing & Alpine Tunnel Closures
Planned truck dosing days in Tyrol, restrictions on the Brenner route and closures of the main Alpine road tunnels.
🚦 Tyrol truck dosing (Blockabfertigung) at Kufstein
On these days Tyrol lets only a limited number of trucks per hour enter Austria at Kufstein-Nord (A12, coming from Germany on the A93 towards Innsbruck and the Brenner). Expect long queues on the A93 in Bavaria. Dosing starts at about 05:00 and usually lasts the morning. Tyrol can add extra days at short notice.
Where: A12 Kufstein-Nord, southbound (from Germany)
| Date | Start |
|---|---|
| Wednesday, 9 December 2026 | 05:00 |
| Thursday, 7 January 2027 | 05:00 |
| Monday, 11 January 2027 | 05:00 |
| Monday, 18 January 2027 | 05:00 |
| Monday, 25 January 2027 | 05:00 |
| Monday, 1 February 2027 | 05:00 |
| Monday, 8 February 2027 | 05:00 |
| Monday, 15 February 2027 | 05:00 |
| Monday, 22 February 2027 | 05:00 |
| Monday, 1 March 2027 | 05:00 |
| Monday, 8 March 2027 | 05:00 |
| Monday, 15 March 2027 | 05:00 |
- Land Tirol – Dosierkalender 2026 (PDF)
- Land Tirol – Dosierkalender Q1 2027 (PDF)
- ADAC – current dosing / Blockabfertigung
🌉 Brenner motorway A13 – Lueg bridge
The Lueg bridge on the A13 Brenner motorway carries only one lane in each direction (two lanes only on selected high-traffic days) while a new bridge is built – works are planned until 2030. Expect congestion, especially on Mondays, Fridays and Saturdays. Additional truck driving bans on some Saturdays in early 2027 are under discussion and not yet confirmed.
⛰️ Alpine tunnel closures
Planned night closures of the main road tunnels between France and Italy. Operators publish provisional schedules – check the operator before you leave.
| Tunnel | Dates | Time | Closure |
|---|---|---|---|
| Mont Blanc (FR–IT) | Mon, 14 Dec 2026 – Thu, 17 Dec 2026 | 22:00–06:00 | Full closure, both directions (every night) provisional |
| Fréjus (FR–IT) | Mon, 30 Nov 2026 – Thu, 3 Dec 2026 | 23:00–06:00 | Full closure, both directions (every night) provisional |
| Fréjus (FR–IT) | Thu, 10 Dec 2026 | 23:00–06:00 | Full closure, both directions (every night) provisional |
Mont Blanc tunnel: a full closure of about 15 weeks is planned in autumn 2027 (and again in 2028). Exact dates have not been announced yet.
Information is for guidance only and can change at short notice. Always check the official sources before dispatch. Last reviewed: 24 November 2026.